PM Vault ← All guides

Home / Guides / Project dashboards

Reporting & control

What belongs on a project dashboard (and what to cut)

A good dashboard isn't a wall of charts — it's the smallest set of numbers that lets someone make a decision in sixty seconds. Most project dashboards fail because they decorate a status report instead of driving one.

The one test every dashboard tile must pass

Before a metric earns a place on the page, it has to answer: "if this number moves, does someone do something different?" If the answer is no, it's decoration — cut it. A task-count that never changes a decision is noise dressed up as rigour. The best dashboards are ruthless about this; they'd rather show six numbers that matter than forty that don't.

The five things worth tracking

Across almost every project, decision-driving information falls into five lanes:

LaneThe question it answersLead metric
ScheduleWill we finish on time?SPI, milestone variance, forecast finish
CostWill we finish on budget?CPI, forecast at completion (EAC)
ScopeAre we still building the agreed thing?change requests, scope added vs baseline
RiskWhat could still go wrong?top exposures, trend, P80 finish
Flow (agile)Is delivery steady?throughput, cycle time, WIP

Two of these — cost and schedule — are best expressed through earned value, because CPI and SPI put time and money on the same comparable scale. Risk is best expressed as a forecast range (P50/P80), not a single date.

RAG status, done honestly

Red/Amber/Green is the most abused device in project reporting. "Green" too often means "I don't want a hard conversation this week." A defensible RAG has rules, not moods:

  • Green — forecast within tolerance on time and cost; no unmitigated high risks.
  • Amber — forecast breaching a threshold, with a recovery plan in hand.
  • Red — forecast breaching, no agreed recovery, or a high risk realised.

Write the thresholds down once and apply them mechanically. A status that anyone can audit against the numbers is worth ten that depend on the reporter's optimism.

The watermelon problem: green on the outside, red in the middle. It happens whenever status is a feeling instead of a calculation. Tie every colour to a number on the same page and the watermelon can't form.

Lead vs lag: show the windscreen, not the mirror

"Tasks completed this month" is a lag indicator — it tells you about the past. "Forecast finish date" and "CPI trend" are lead indicators — they tell you where you're heading. A dashboard built only from lag metrics is a rear-view mirror; you'll see the wall after you hit it. Weight the page toward forecasts and trends.

One page, one source of truth

If schedule lives in one tool, cost in a spreadsheet, and risk in someone's head, your "dashboard" is really three arguments waiting to happen. The value of a single control sheet is that every tile is computed from the same underlying data, so the numbers can't quietly disagree. When the board asks how a figure was derived, you open it — you don't go hunting.

Keep it defensible

The final rule ties the rest together: every number on the dashboard should be traceable to its inputs. A RAG you can't explain, a percentage nobody can reproduce, a forecast with no method behind it — these are exactly the figures that collapse under one sharp question in a steering committee. Build the page so that opening any tile shows the working.

A one-page control system that computes every tile

The Day-One Toolkit is a 40-sheet Excel control system — schedule, earned value, 5×5 risk and agile flow — that rolls up to a single board-ready dashboard, every formula visible and offline. Start with the free Field Guide.