The problem EVM solves
"We've spent 60% of the budget" tells you nothing on its own. Spent 60% to deliver 80% of the work? You're ahead. Spent 60% to deliver 40%? You're heading for an overrun. Cost without progress is meaningless, and progress without cost is just as blind. Earned Value Management puts the two on the same axis — money — so schedule and budget can finally be compared in one number.
The three measurements everything is built from
EVM starts with three values, all expressed in currency:
- Planned Value (PV) — the budgeted cost of the work you planned to have done by now. Also called BCWS.
- Earned Value (EV) — the budgeted cost of the work you've actually completed. Also called BCWP. This is the heart of the method.
- Actual Cost (AC) — what that completed work actually cost you. Also called ACWP.
The whole budget at completion is the BAC (Budget At Completion).
The variances: are you ahead or behind?
Cost Variance (CV) = EV − AC
Both follow the same rule: positive is good, negative is trouble. A negative SV means you've earned less value than you planned to by now — you're behind schedule. A negative CV means the work cost more than it was budgeted for — you're over cost.
The performance indices: CPI and SPI
Variances tell you the size of the gap; the indices tell you the rate, which is what you forecast with.
Schedule Performance Index (SPI) = EV ÷ PV
Read them as efficiency. CPI of 0.80 means you're getting 80 cents of value for every dollar spent. SPI of 1.10 means you're earning value 10% faster than planned. Anything below 1.0 is a warning; above 1.0 is a cushion.
A worked example
A project has a total budget (BAC) of $100,000 over 10 months. At month 5 you'd planned to be halfway, so PV = $50,000. You check the actuals:
| Measure | Value | Meaning |
|---|---|---|
| PV | $50,000 | planned to be 50% done |
| EV | $40,000 | actually 40% done |
| AC | $55,000 | spent so far |
Now the diagnosis falls out:
- SV = 40,000 − 50,000 = −$10,000 → behind schedule.
- CV = 40,000 − 55,000 = −$15,000 → over cost.
- SPI = 40,000 ÷ 50,000 = 0.80 → working at 80% of planned pace.
- CPI = 40,000 ÷ 55,000 = 0.73 → 73 cents of value per dollar.
This project is in real trouble on both axes — and you knew it at the halfway mark, not at the end.
Forecasting where you'll land
The most valuable thing EVM does is project the final cost — the Estimate At Completion (EAC). The common form assumes today's cost efficiency continues:
In our example: 100,000 ÷ 0.73 = ~$137,000. The project budgeted at $100k is forecast to finish around $137k unless something changes. The Estimate To Complete (ETC = EAC − AC) is the cash you still need: ~$82,000. The Variance At Completion (VAC = BAC − EAC) is the projected overrun: −$37,000.
Why this matters in the room: "We might be a bit over" gets waved away. "Current efficiency forecasts a $37,000 overrun, and here is the CPI it's based on" gets a decision. EVM turns a feeling into a defensible number.
The standards behind it
EVM is not a vendor invention — it's codified. The core method aligns with the PMBOK® Guide and is formalised in ANSI/EIA-748; the schedule-forecasting refinement (Earned Schedule) extends SPI into time units so it stays reliable late in a project. PM Vault cites these as authority and reproduces none of them — see our sources.
Doing it without a server
You don't need an enterprise platform to run EVM. A well-built spreadsheet computes every value above the moment you enter actuals — and because the formulas are visible, you can defend each one. When the spreadsheet isn't enough, a dedicated instrument runs live earned value and Earned Schedule for you, on your machine, showing its working.
Run earned value on your own data — offline
The Day-One Toolkit is a 40-sheet Excel control system with earned value, schedule, 5×5 risk and agile flow built in — every formula open, nothing phoning home. Start free with the Field Guide, or step up to the full Field Manual.